Stanley J. Aronoff Laboratory

Description
The alternate name for this building is the Life Sciences Reserach Building. It is located at 318 West 12th Ave between Botany and Zoology (Jennings) and the 12th Avenue Parking Garage. It is a seven story building with a gross floor area of 107,593 sq. ft. The budget for the project was $24,680,696. Timeline: 1. The architect/engineer contract was approved on April 3, 1997 2. The schematic design was approved on June 18, 1998 3. The design development document was approved on October 23, 1998 4. Construction document approval was on November 5, 1999 5. Bid opening on August 1, 2001 6. Contracts were awarded to contractors on September 28, 2001 7. Construction began on October 5, 2001 8. Completion May 28, 2003 9. Report of award to the Board of Trustees on November 2, 2001